01 General information02 Specifications03 Manufacturing data and tolerances04 Tightening torques05 Fluids and lubricants06 Maintenance07 Diagnostic checks08 Engine09 Clutch10 Gearbox and differential11 Axles and driveshafts12 Brakes13 Steering14 Suspension and wheels15 Heating, air conditioning and auxiliary units16 Electrical equipment17 Body fittings18 Body panels and frame19 Wiring diagrams and electrical functions20 Wiring harnesses21 Connectors and pin-outs22 Fault diagnosis23 Special tools
Fiat Ulysse Factory Service Manual (2002-2010)08 · Engine
08 · Engine

E.g.r. system solenoid - r + r

Make
Fiat
Model
Ulysse Factory Service Manual
Year
2002–2010
Section
Exhaust emission control system › E.g.r. system solenoid - r + r
EngineE.g.r. system solenoid - r + r

E.G.R. SYSTEM SOLENOID - R + R

Operation 1080C24 · EXHAUST GAS RECIRCULATION SYSTEM (E.G.R.)

2.0 16V JTD

Removing

1. Disconnect the electrical connection.

2. Release the vacuum pipes.

3. Undo the retaining nuts.

4. Release and remove the solenoid valve.

E.G.R. SYSTEM SOLENOID - R + R

Refitting

- Place the solenoid valve in position and tighten the fixing nuts.

- Connect the vacuum pipes and the electrical connection.

2.0 16v

Removing

Op. 5530B56 BATTERY DRIP TRAY COVER - R.R.

- Disconnect the negative battery terminal.

Op. 5010B18 CLIMATE CONTROL UNIT AIR INTAKE - R.R.

1. Rotate the fastening pins (1a) through 90° and remove the coil cover (1b).

E.G.R. SYSTEM SOLENOID - R + R

1. Disconnect the electrical connection for the E.G.R. solenoid valve.

2. Undo the fixing bolts (2a) and remove the E.G.R. solenoid valve (2b).

E.G.R. SYSTEM SOLENOID - R + R

Refitting

- Fit the E.G.R. system solenoid valve and tighten the fixing bolts.

- Connect the electrical connection for the E.G.R. solenoid valve.

- Fit the coil cover and rotate the fastening pins through 90° to secure it.

Op. 5010B18 CLIMATE CONTROL UNIT AIR INTAKE - R.R.

- Connect the negative battery terminal.

Op. 5530B56 BATTERY DRIP TRAY COVER - R.R.

2.2 16V JTD

Removing

1. Disconnect the electrical connection.

2. Release the vacuum pipes.

3. Undo the retaining nuts.

4. Release and remove the solenoid valve.

E.G.R. SYSTEM SOLENOID - R + R

Refitting

- Place the solenoid valve in position and tighten the fixing nuts.

- Connect the vacuum pipes and the electrical connection.